Schedule and Milestones

Planned Delivery Schedule

Phase Period Milestone
Contract signing 2022 FMS Letter of Offer and Acceptance (LOA)
Production start 2024--2025 Swiss F-35A in Lot 18/19
Bulkhead signature 21.09.2026 Swiss delegation (Chief of the Armed Forces, head of armasuisse, Air Force commander) signs the forward fuselage bulkhead of the first Swiss F-35A at the Lockheed Martin plant in Fort Worth (Texas); a symbolic event with no technical function [114]
First delivery from mid-2027 The first eight Swiss F-35A will be used from mid-2027 at Ebbing Air National Guard Base (Arkansas) to train pilots and ground crew, and then gradually transferred to Switzerland [114]
Pilot training 2025--2028 Training in the USA (Luke AFB, Arizona); from mid-2027 also on Swiss F-35A at Ebbing (Arkansas) [114]
RIGI final assembly 2028--2029 4 units in Emmen (RUAG)
Initial Operating Capability (IOC) ~2030 First operational readiness
Full Operating Capability (FOC) ~2032 Full operational readiness of the entire fleet
F/A-18 retirement 2030--2035 Gradual transition

Basing and Infrastructure

Location Canton Function
Payerne VD Main base, investment ~CHF 250 million over 10 years [47]; F-35A stationed from mid-2028 [114]
Emmen LU RIGI final assembly, RUAG maintenance centre; F-35A stationed from 2032 [114]
Meiringen BE Alpine base, investment ~CHF 68 million [47]; F-35A stationed from 2030 [114]

Infrastructure costs rose from an original CHF 120 million to CHF 200 million -- an increase of 67% [47]. Building permits for two bases are delayed until at least mid-2026 [47].

Infrastructure Modifications

The following modifications are required at all locations:

  • Hangar conversions for stealth maintenance
  • Stealth maintenance hangars with controlled environment
  • F135 engine test stands
  • Full Mission Simulator (FMS) for pilot training
  • ODIN system integration (successor to ALIS) for maintenance and spare parts management

Risk Factors for the Schedule

The following risks could affect the schedule:

  • TR-3 delays: The Swiss F-35A are to be delivered with TR-3. TR-3 is already delayed for Lot 15 [36][38].
  • Building permits: Infrastructure projects are delayed until at least mid-2026 [47]
  • Global supply chain: In 2024, all 110 F-35s produced were delivered late -- on average 238 days [36]

Critical Factual Analysis

The following sections analyse, based on publicly available original sources -- GAO reports, DOT&E reports, CBO studies and recognised specialist media --, what the Swiss Air Force will actually receive.


References

[36] armasuisse. Air2030 FAQ F-35A
[38] news.admin.ch. (2025). Pilatus Receives Access to F-35A Technology
[47] Defense Aerospace. Switzerland to Invest Over CHF 1.1 Billion to Prepare Air Bases for F-35A
[114] armasuisse / DDPS. (2026). Swiss delegation signs first F-35A – production and delivery of the fighter aircraft on track. Press release of 22.09.2026